Back to search

Pilgrim's Pride - Natchitoches Poultry Processing

Parent Companies:
Pilgrim's Pride Corporation
EPA Facility ID:
100000061078
Other ID:
71457CNGRBHWY1B
Facility DUNS:
141080395
Parent Company DUNS:
7334170

Location:

Address:
Hwy 1 South ByPass
Natchitoches, LA 71457
County:
NATCHITOCHES
Lat / Long:
31.725, -93.107 (Get map)
Method:
Interpolation - Satellite
Description:
Center of Facility
Horizonal accuracy:
10 m
Horizontal reference datum:
World Geodetic System of 1984
Source map scale:

Owner/Operator:

Name:
Pilgrim's Pride Corporation
Phone:
(970) 506-8000
Address:
1770 Promontory Circle
Greeley, CO 80634
Foreign Address:

Person responsible for RMP implementation:

Name:
Linda J. McDaniel
Title:
Corporate PSM Director

Emergency contact:

Name:
Larry Payne
Title:
Maintenance Manager
Phone:
(318) 352-9600
24-hour phone:
(318) 332-3535
Ext or PIN:

Other contacts:

Facility (or company) email:
Facility phone:
(318) 352-9600
Facility (or company) URL:

Safety:

Local Emergency Planning Committee:
Natchitoches LEPC
Full-Time Equivalent Employees:
561
Covered by OSHA PSM:
Yes
EPCRA section 302:
Yes
CAA Title Air Operating Permit:
No
CAA Permit ID#:
OSHA Star/Merit Ranking
No
Last Safety Inspection Date:
Nov. 21, 2013
Inspecting Agency:
State environmental agency
Using Predictive Filing:
No

Processes:

Ammonia Refrigeration (1)
RMP ID:
1000053913
CBI claimed:
No
Program Level:
3
NAICS:
Poultry Processing (311615)
Chemical name
CAS#
Quantity (lbs.)
CBI
Ammonia (anhydrous)
7664-41-7
34,000
No
Public OCA Chemical
0
No
Ammonia Refrigeration (2)
RMP ID:
1000053914
CBI claimed:
No
Program Level:
3
NAICS:
Poultry Processing (311615)
Chemical name
CAS#
Quantity (lbs.)
CBI
Ammonia (anhydrous)
7664-41-7
16,000
No
Public OCA Chemical
0
No

RMP Preparer:

Name:
Address:

,
Foreign Address:

Phone:

Latest RMP Submission:

Date:
June 17, 2014
Type:
Resubmission
Reason:
5-year update (40 CFR 68.190(b)(1))
Registered:
Yes
RMP ID:
1000043648

Deregistration:

Date:
Effective Date:
Reason:
Other Reason:

2. Toxics: Worst-case

Some Risk Management Plan information is not provided in the available RMP data. You need to make an appointment at an EPA Reading Room In order to get access to details from the Off-Site Consequence Analysis (OCA) such as:

Instructions on how to make an EPA appointment can be found here.

Public OCA Chemical (in Ammonia Refrigeration (1))
CBI claimed:
No
Percent weight:
100.0
Physical state:
Gas liquified by pressure
Model used:
EPA's RMP*Comp(TM)
Release duration (mins):
10.00
Wind speed (meters per sec):
1.5
Stability class:
F
Topography:
Rural
Passive mitigation
considered:
  • None
not considered:
  • Dikes
  • Enclosures
  • Berms
  • Drains
  • Sumps

3. Toxics: Alternative release

Some Risk Management Plan information is not provided in the available RMP data. You need to make an appointment at an EPA Reading Room In order to get access to details from the Off-Site Consequence Analysis (OCA) such as:

Instructions on how to make an EPA appointment can be found here.

Public OCA Chemical (in Ammonia Refrigeration (1))
CBI claimed:
No
Percent weight:
100.0
Physical state:
Gas liquified by pressure
Model used:
EPA's RMP*Comp(TM)
Wind speed (meters per sec):
3.00
Stability class:
D
Topography:
Rural
Passive mitigation
considered:
  • None
not considered:
  • Dikes
  • Enclosures
  • Berms
  • Drains
  • Sumps
Active mitigation
considered:
  • None
not considered:
  • Sprinkler systems
  • Deluge systems
  • Water curtain
  • Neutralization
  • Excess flow valve
  • Flares
  • Scrubbers
  • Emergency shutdown
Public OCA Chemical (in Ammonia Refrigeration (2))
CBI claimed:
No
Percent weight:
100.0
Physical state:
Gas liquified by pressure
Model used:
EPA's RMP*Comp(TM)
Wind speed (meters per sec):
1.50
Stability class:
D
Topography:
Rural
Passive mitigation
considered:
  • None
not considered:
  • Dikes
  • Enclosures
  • Berms
  • Drains
  • Sumps
Active mitigation
considered:
  • None
not considered:
  • Sprinkler systems
  • Deluge systems
  • Water curtain
  • Neutralization
  • Excess flow valve
  • Flares
  • Scrubbers
  • Emergency shutdown

4. Flammables: Worst-case

None

5. Flammables: Alternative release

None

6. Five-year accident history

No Registered Accidents

7. Prevention: Program level 3

Ammonia Refrigeration (1), Poultry Processing (311615)
Prevention Program ID:
1000045267
Safety Review Date
Dec. 31, 2013, since latest RMP submission
PHA Update Date
July 14, 2011, since latest RMP submission
PHA Techniques
  • What if/Checklist
Hazards Identified
  • Toxic release
  • Fire
  • Explosion
  • Overpressurization
  • Corrosion
  • Overfilling
  • Contamination
  • Equipment failure
  • Cooling loss
Process Controls
  • Relief Valves
  • Check Valves
  • Manual Shutoffs
  • Automatic Shutoffs
  • Interlocks
  • Alarms
  • Backup Pump
Mitigation Systems
  • Fire Walls
  • Enclosure
Monitoring Systems
  • Process Area
Changes since PHA
  • None
Training Type
  • Classrom
  • On the Job
Competency Testing
  • Written Test
  • Demonstration
  • Observation
Procedure Review Date
May 1, 2014, since latest RMP submission
Training Review Date
May 2, 2014, since latest RMP submission
Maintenance Review Date
May 2, 2014, since latest RMP submission
Maintenance Inspection Date
May 4, 2014, since latest RMP submission
Equipment Tested
Yes
Management of Change Most Recent Date
April 26, 2014
Management of Change Review Date
April 26, 2014
Pre-startup Review Date
Sept. 27, 2013
Compliance Audit Date
May 16, 2013
Compliance Audit Change Completion Date
Dec. 31, 2015
Incident Investigation Date
May 17, 2013
Incident Invest. Change Completion Date
May 24, 2013
Participation Plan Review Date
Dec. 24, 2013
Hot Work Review Date
May 20, 2013
Contractor Safety Review Date
Jan. 25, 2013, since latest RMP submission
Contractor Safety Eval. Date
Feb. 26, 2014, since latest RMP submission
Ammonia Refrigeration (2), Poultry Processing (311615)
Prevention Program ID:
1000045268
Safety Review Date
Dec. 31, 2013, since latest RMP submission
PHA Update Date
July 24, 2011, since latest RMP submission
PHA Techniques
  • What if/Checklist
Hazards Identified
  • Toxic release
  • Fire
  • Explosion
  • Overpressurization
  • Corrosion
  • Overfilling
  • Contamination
  • Equipment failure
  • Cooling loss
Process Controls
  • Relief Valves
  • Check Valves
  • Manual Shutoffs
  • Automatic Shutoffs
  • Interlocks
  • Alarms
  • Backup Pump
Mitigation Systems
  • Enclosure
Monitoring Systems
  • Process Area
Changes since PHA
  • None
Training Type
  • Classrom
  • On the Job
Competency Testing
  • Written Test
  • Demonstration
  • Observation
Procedure Review Date
May 1, 2014, since latest RMP submission
Training Review Date
May 2, 2014, since latest RMP submission
Maintenance Review Date
May 2, 2014, since latest RMP submission
Maintenance Inspection Date
April 26, 2014, since latest RMP submission
Equipment Tested
Yes
Management of Change Most Recent Date
April 26, 2014
Management of Change Review Date
April 26, 2014
Pre-startup Review Date
Sept. 27, 2013
Compliance Audit Date
May 16, 2013
Compliance Audit Change Completion Date
Dec. 31, 2015
Incident Investigation Date
May 17, 2013
Incident Invest. Change Completion Date
May 24, 2013
Participation Plan Review Date
Dec. 24, 2013
Hot Work Review Date
May 20, 2013
Contractor Safety Review Date
Jan. 25, 2013, since latest RMP submission
Contractor Safety Eval. Date
Feb. 26, 2014, since latest RMP submission

8. Prevention Program level 2

No Prevention Program level 2

9. Emergency response

Facility In Community Plan:
No
Facility Own Response Plan:
No
Specific Facility Response Plan:
Yes
Inform. Procedures in Response Plan:
No
Emergency Care in Response Plan:
Yes
Plan Review Date:
Response Training Date:
Jan. 31, 2014
Local Response Agency:
Local Response Agency Phone:
(318) 357-3860
Subject To - OSHA EAP:
No
Subject To - OSHA HAZWOPER:
Yes
Subject To - CWA:
No
Subject To - RCRA:
No
Subject To - OPA:
No
Subject To - State EPCRA:
Yes
Subject To - Other:

Executive Summary

This Executive Summary is to inform all interested persons, including employees that the Pilgrim's Pride - Natchitoches Poultry Processing Facility - Natchitoches, LA is complying with OSHA's Process Safety Management Standard (PSM) Title 29 Code of Federal Regulations (CFR) 1910.119 and EPA's Risk Management Program regulations (RMP) Title 40 CFR Part 68, to deal with the risks involved with the storage, handling, and processing of hazardous chemicals. In this way we promote overall plant, employee and public safety.



These programs help this facility to prevent the occurrence, and minimize the consequences, of significant releases of toxic substances as well as fires, explosions, and other types of catastrophic accidents. Overall, these programs help prevent accidental fatalities, injuries and illnesses and avoid physical property damage. Our safety programs are applied to any activity involving hazardous chemicals including any use, storage, manufacturing, handling, or the on-site movement of such chemicals, or combination of these activities. This facility has two refrigeration systems using Anhydrous Ammonia as the refrigerant. The amount of Anhydrous Ammonia contained in each system is above the EPA threshold reporting quantity required to comply with the RMP standards.



Pilgrim's Pride is committed to the safety of its employees and the surrounding community. This commitment includes both human health and the protection of the environment. Safety is ensured through careful preventative measures and emergency planning. The intent of our release prevention policy is to minimize all potential risks that could possibly lead to an accidental ammonia release. This program focuses primarily on the safe operation and the mechanical integrity of the process equipment. Our safety programs help to prevent accidents because they focus on rules, procedures, and practices which govern individual processes, activities or pieces of equipment. These rules are detailed
and improved as necessary. They are also communicated to and accepted by all employees at the facility.



This facility's emergency response program is based on the OSHA requirements for Emergency Action Plans (OSHA 29 CFR 1910.38 and 1910.119) and HAZWOPER (OSHA 29 CFR 1910.120). This program includes an emergency response notification plan, emergency response drills and drill evaluations. We have trained employees for emergency response and maintain a written emergency response plan. This plan is coordinated with the local Fire Department and ensures that employees are trained on the proper response to an emergency situation.



This facility has NOT experienced a recordable Ammonia release in the past five years.



This facility is in the process of implementing Ammonia Process Safety Management Inc. (APSM), a powerful online tool to enable comprehensive and companywide standardization of PSM and RMP compliance related elements. Pilgrim's Pride and this facility will use this system to manage its compliance programs in an easily accessible online format that is also consistent, efficient, and provides effective control from the top down to enhance collaboration, efficiency, reporting and accuracy.